If 5 workers can pave 10 driveways in 30 days, how many days would it take 20 workers to pave 38 driveways?

Respuesta :

musiclover10045
musiclover10045 musiclover10045
  • 25-07-2017

5*30/10 = 20x/38

150/10 = 20x/38 =

5700/200x=

x= 5700/200 = 28.5 days

Answer Link

Otras preguntas

what is the credit card balance? A-The amount of interest you must pay the credit card company. B-The required minimum payment to your credit card company. C-A
Pythagorean Theorem: Alex leaves home, travels 5 miles east, and arrives at the library. He leaves the library and travels 3 miles north to a friend's house.
Desert animals need to concentrate urine. What structural changes in the kidney would be associated with a kidney that is exceptionally good at concentrating ur
In a population of skunks, there are striped and stripeless individuals. Stripes are dominant to the absence of stripes. In this population, p = 0.8 and the fre
statement and reasons m<1 +m<2+ m<3=180 whats the reason?
If 1+4=5; 2+5=12; 3+6==21; what is 8+11
list the six external parts of a computer system and identify which are output and which and which are input devices
What's x² + 2x + 1 factorised?
Which Of The Following Can Be Found In Breast Milk? 1. Vitamin D 2. Calcium 3. Anti Bodies 4. Iron
which branch of central government makes/enact/ passes laws