20 men can do a piece of work in 24 days. After working for few days, 3 men are added and the work was finished 3 days earlier. After how many days if 4 men are added?​

Respuesta :

sidwambua sidwambua
  • 29-06-2021

Answer: 17 and a half

Step-by-step explanation:

M    D    W

20  24  480

20   21  420

24   17 and a half  420

= 17 and a half

Answer Link

Otras preguntas

How does Boxer and his motivations and conflicts have affected the plot in Animal Farm? ​
kathy is baking cakes.each cake requires 1/12 of a teaspoon of vanilla and she has 9/12 of a teaspoon,how much cakes can she bake
Help me ASAP!!!! Don’t have to explain
A triangular flowerbed is being planted inside a circular area of grass. What is the area of the triangular flowerbed? (Use 3.14 for π.) 1,350 ft 2 1,566 ft 2 1
Pleaseeee helppp.....
help please! John f Kennedy question​
How is the titanic and it’s sinking a good introduction to the topic of social stratification? Provide 3 examples of how class makes a difference
1. What are transition metals?
use the word immoral in a sentence
It’s question number 6, please help!