if 8 people can pick the apples from the trees in 6 days, how long will it take 12 people

Respuesta :

mhanifa
mhanifa mhanifa
  • 24-06-2020

Answer:

4 days

Step-by-step explanation:

8 people can do the job in 6 days, job is this case is picking apples.

  • The amount of the job (apples) is same and the only variable is number of people which changes the time accordingly.  

1 person can do same job for 6*8= 48 days

12 people can do same for 48/12= 4 days

Answer Link

Otras preguntas

Which of the following is MOST likely to result in a hydrogen bond? 1) A water molecule with another water molecule 2) An ion with another ion 3) A nonpolar mol
Someone Please help me answer this question.
Based on the passage how have conflicts changed cassius?
Two point charges each with a charge of +1,00c are separated by a distance of1.0m what is the magnitude of the force between them
All of the following are ways that enterprise systems add business value except: Select one: a. increase operational efficiency b. help enforce standard practic
Natural selection is a mechanism that acts on individuals within a population. Which is a result of the process of natural selection? The reproductive rate of t
Distribute 7 x (2+2x)
what is economic equality​
2. Fill in the table below by writing the complementary strand of DNA that would be formed by each template strand. (4 points) Hint: C pairs with G, and T pairs
Question 5: Please help, is it C?