A manufacturer planned to use $97 of materials per unit produced, but in the most recent period it actually used $95 of material per unit produced. During this same period, the company planned to produce 2,850 units, but actually produced only 2,500 units. The flexible-budget variance for materials, to the nearest dollar, is: