The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

What particles make up the nucleus of an atom?
the perimeter of a rectangle is 120 meters. If the length of the rectangle is 20 meters more than the width, what are the dimensions of the rectangle.
Find the slope of the ski run that descends 15 feet for every horizontal change of 24 feet
98 divided by 7 please show how
factor: 6x+36=  how do I solve this problem
98 divided by 7 please show how
the perimeter of a rectangle is 120 meters. If the length of the rectangle is 20 meters more than the width, what are the dimensions of the rectangle.
What are the unit rates for  4/8 , 5/25, 36/6, 14/21, 18/30, 28/16, 56/35, 45/108, 12/42, 39/26
Find the slope of the ski run that descends 15 feet for every horizontal change of 24 feet
factor: 6x+36=  how do I solve this problem