A project management plan is the main output of the project ________ knowledge area.

Respuesta :

ariston ariston
  • 21-08-2018

A project management plan is the main output of the project Integration management knowledge area

Explanation: The Project integration management which is the first of the 10 PMBOK knowledge areas involves developing a project charter and project management plan

Answer Link

Otras preguntas

The radioactive substance cesium-137 has a half-life of 30 years. The amount A(t) (in grams) of a sample of cesium-137 remaining after t years is given by the f
0.4 how it come[tex]10 \div 10[/tex]​
How does the process of solving an inequality with variables on both sides compare to solving an equation with variables on both sides?
the velocity time graph for a cycle is shown. work out the total distance travelled on the cycle. work out the acceleration in the last 8 seconds. Need the answ
Explain one way organisms with similar niches reduce competition when they are found in the same ecosystem? Give one example.
a rope 5m long is fastened to two hooks 4.0m apart on a horizontal celling. to the rope is attached a 10kg mass so that the segments of the rope are 3.0m and 2.
Please help with this question
2 What is the derivative of the function f(x) = 3x² + 2√x - 4x at x=1?​
does energy play an important role in global warming? pls answer quick - ill give u all my points
Please help will mark Brainly