M can do a piece of work in 20 days. He works at it alone for 5 days and N alone finishes the remaining work in 9 days. In how many days, both of them together can complete the work ?
1. 12.5 days
2. 8 days
3. 10 days
4. 7.5 days

Respuesta :

Otras preguntas

A dangling modifier is a A. word that's unnecessary to the rest of the sentence's meaning. B. group of words in the wrong position in a sentence.
Which choices are common factors of the numerator and denominator of the fraction? 21/28
Line segment YZ was used to translate ABCDE. YZ is 6.2 inches long. What is the length of AA'+BB'+CC'+DD'+EE'?
This number represents the number of times the base is used as a factor
If four points are collinear are they coplanar
Why is it difficult, using the traditional definition of species to classify some bacteria and archaea at the species level?
70% of what number is 224?
Structure of the atmosphere: beginning at the surface of the earth, list, in order, the layers of the atmosphere.
8 hundreds 4 tens = 84 blank
The line segments are translated 2 units to the left to form J′K′ and M′N′. Which statement describes J′K′ and M′N′?